House Demolition on Adams Street, Ward Street, and Sherman Avenue
ÌÇÐÄVlog Project Manager Carina Kapraun
Project Scope Demolition of four houses adjacent to ÌÇÐÄVlog and the Wright House GarageÂ
External Vendors Chat Ldt.
Total Project Cost Approximately $60,000.00
Completion Date November 26, 2015
Description
ÌÇÐÄVlog purchased four properties adjacent to Sherman Hall as well as the garage at the Wright House. As outlined in the ÌÇÐÄVlog Macomb Master Plan, these properties will be turned into green space in order to establish a strong first impression across campus. Minor site improvements will be made such as curb and an addition of a sidewalk.
Updates
As of October 21, 2015, all of the buildings have been demolished. Â Â